Project Phase | Date Money available in Brazil | From | To | Duration (Days) | Activities | Cost Involved (Brazilian Real) | Cost Involved(Euro, Real/Euro conversion rate from date 16/11/2012) |
I | 41214 | 01/11/12 | 16/11/12 | 16 | Purchase and storage of material, preparation of the site and started the foundations | R$ 6.190,00 | €2.392,67 |
II | 16/11/2012 | 16/12/2012 | 30 | Foundation, structure, masonry (walls) Electrical wiring, plumbing (water and sewer), frames (windows and openings) and coverage (structure and roof, lined) | R$ 3.500,00 | €1.500,00 | |
III | 16/12/2012 | 15/01/2013 | 30 | Plastering, painting, flooring, finishes, doors, baseboards, light fixtures, outlets and switches, installation of sanitary wares and metals. Clean the work | R$ 2.810,00 | €1.107,33 | |
R$ 12.500,00 | €5.000,00 | ||||||
Project Kick-off date | 01/11/2012 |
About
We are happy to tell everybody that HESpace approved our 2013 project! This blog will report the project's follow up and results. We've imported the posts from last year's project's blog to make it easy for everyone do see the whole story from the beginning.
sexta-feira, 16 de novembro de 2012
First pictures and follow up
This week, we started the first phase. Check the pictures of the building site and the timeline.